by Sharon Michaels WORDEN — The Huntley Project School Board, JGA Architects president Terry Sukut and construction manager at risk Brent Sumner held a work meeting on Tuesday, April 13 to review “add alternates,” a list of extra items for…
Tag: Wes Coy
Negotiations under way at HP, teachers seek 4.5 percent increase
by Sharon Michaels WORDEN — The Huntley Project teachers’ union has asked for a one-year contract with a 4.5 percent increase in wages and a $25 increase to help pay insurance costs. The Huntley Project Education Association (HPEA) met with…
No mill levy needed at HP as construction gets under way
by Sharon Michaels WORDEN – In two weeks, we should be pouring concrete, reported Brent Sumner to the Huntley Project school board on Tuesday, March 16. Sumner is the construction manager for Fisher Construction. “The ground is now frost free…
Deal to buy Dassinger land for school in limbo
by Robert Nolte WORDEN — Though the asking price is high, the Huntley Project school district is not closing the door on possible purchase of the Dassinger property. The family would like $200,000 for the land being eyed for parking…
With bond process complete, district complimented on its diligence; insurance total now over $7.5 million
by Sharon Michaels WORDEN -The taxable General Obligation School Building Bonds, Series 2009 Qualified School Construction Bonds for financing the the $9,750,000 Huntley Project School successfully closed today, Supt. Wes Coy reported to the school board on Tuesday, Dec. 15.…